For countless sellers, every port suspension and round of congestion directly impacts vessel space availability, transit reliability and logistics costs.
From July to August this year, coastal East China has been hit by successive typhoons. Repeated weather disruptions have triggered a cycle of suspension‑resumption‑congestion relief at Ningbo‑Zhoushan Port, adding new uncertainties to pre‑peak‑season supply chains.
Recently, Typhoon Dolphin, the 13th typhoon of the year, brought gale‑force winds and heavy rain toward coastal eastern Zhejiang. Ningbo‑Zhoushan Port implemented full‑port suspension starting at 18:00 on August 7, with all operating vessels evacuated to anchorages for shelter. Prior to this event, Typhoon Bavi had already disrupted terminal operations and depleted the port’s operational buffers. The prolonged full‑port shutdown caused by Dolphin further amplified cargo backlogs.
While port operations resumed rapidly once weather conditions eased, restarting work does not mean a full return to normal. The port is now operating at high capacity with partial, persistent congestion.
Extreme weather not only exposes vulnerabilities in global supply chains but also tests the emergency resilience of world‑class megaports. It is also forcing the cross‑border logistics industry to shift from price‑driven competition toward risk‑resistance capabilities.
01 After the Storm: Realities of Cargo Backlogs Post‑Suspension‑and‑Restart
Resumption marks only the starting point for congestion mitigation. Pressures accumulated during shutdowns are released in concentrated volumes after services resume:
-
Mass vessel arrivals extend waiting‑at‑berth times
According to Kuehne+Nagel SeaExplorer monitoring, the typhoon disruption left more than 400 000 TEU of cargo across core Yangtze‑River‑Delta ports awaiting processing. By August 12, 60 vessels had returned to Ningbo anchorage. Average waiting‑at‑berth time reached approximately 2.26 days as of August 7, nearly 15 hours higher than the prior week. Seven ultra‑large container vessels of over 20 000 TEU capacity were queuing for berths. Their large‑volume loading‑and‑unloading demands occupy berths, quay cranes and other critical resources, further prolonging overall congestion clearance timelines.
-
Port facilities face heavy pressure; scheduling complexity surges
Data from Ningbo Border Inspection Station shows that between 08:00 August 11 and 08:00 August 12, Ningbo port inspected 56 international‑voyage vessels in a single day — hitting the 2026 24‑hour arrival peak. Concentrated return of storm‑evading vessels sharply increases short‑term burdens on port clearance and anchorage dispatching.
-
Ripple effects squeeze profit margins
Extended dwell times for cargo and trucks generate accumulating detention, demurrage and port storage fees. Post‑resumption container‑drop‑off demand spikes push up yard, stevedoring and warehousing rates. Carriers have also tightened free container‑use and port‑window allowances, driving higher overtime surcharges and substantially lifting overall logistics costs for cross‑border businesses.
Note: Figures above reflect snapshots from the early recovery phase; backlogged cargo will require multiple additional days to clear.
02 In‑Depth Analysis: Overlapping Pressures Behind Congestion
This round of congestion stems from multiple stacked existing pressures. Extreme weather merely exposed supply‑demand fissures under high‑volume operating conditions.
-
Elevated throughput leaves limited operational buffers
In H1 2026, Ningbo‑Zhoushan Port handled 27.691 million TEU, an 8.7 % year‑on‑year increase. Against this massive cargo baseline, even brief port suspensions create significant “dam‑burst backlog effects”, leaving little spare capacity within terminal workflows to absorb delays.
-
Worsening global supply‑chain fragility lowers schedule reliability
Persistent Red‑Sea disruptions force vessel rerouting and lengthen transit cycles, depressing global shipping‑schedule on‑time performance. Cascading vessel delays cause clustered arrivals and complicate empty‑container repositioning, further eroding scheduling tolerance margins for ports.
-
Peak‑season cargo surges bring forward operational loads
As traditional export peak season kicks in, many sellers have accelerated shipments. Combined with market expectations of upcoming freight‑rate hikes, cargo rush‑outflows have intensified. Popular trade lanes are already space‑constrained. Typhoon‑related port shutdowns trigger a vicious cycle: delayed port intake → revised vessel schedules → subsequent congestion.
03 Supply‑Chain Mitigation: Resilience Across Terminals and Carriers
Congestion is short‑term pain. Stable supply‑chain performance depends on end‑to‑end collaboration. Resilience‑driven adjustments are unfolding, from port‑side congestion relief to carrier‑level schedule management.
- Port side: Infrastructure enabling high‑volume backlog resolution
Ningbo‑Zhoushan Port draws on scale and smart‑terminal capabilities to digest cargo surges.
‑ Scale advantage: Container throughput exceeded 43 million TEU in 2025, ranking third globally; 309 shipping routes connect more than 700 ports worldwide.
‑ Intelligent scheduling: In‑house vessel‑planning automation compiles stowage plans in 20 minutes, down from 3 hours manually.
‑ Multi‑modal diversion: Road‑rail‑water intermodal transport distributes pressure. Sea‑rail intermodal volume surpassed 2 million TEU in 2025, delivering alternative channels for congestion relief.
*Source: Zhejiang Seaport Group / Ningbo‑Zhoushan Port Group public datasets.
- Carrier side: Route adjustments and capacity controls
Faced with congestion, major carriers including Maersk and ONE have implemented port‑skipping, voyage rescheduling and route optimisation — reshaping logistics experiences for sellers.
‑ Port‑skipping for schedule recovery: Maersk issued multiple skip‑port advisories (e.g. voyage SEASPAN GUAYAQUIL omitted Shanghai calls). ONE’s voyage ONE SPHERE 2633E also skipped Shanghai to recover lost schedule time.
‑ Delayed departures: ONE announced delayed ETDs for multiple sailings including KMTC HAIPHONG and MSC ANNA, with some voyages pushed back up to two weeks.
While port‑skipping and voyage consolidation ease burdens on individual terminals, they drive higher transshipment costs, extend delivery lead‑times and sharply raise risk of cargo roll‑overs, redistributing hazards across the whole supply chain.
Storm risks remain ongoing. Typhoon Saudel, the 18th typhoon this year, formed on August 19. The 2026 typhoon‑season hazard window is not yet closed and continuous vigilance is required.
Sellers are advised to deploy both short‑term operational responses and long‑term strategic planning to build resilient supply chains. Integrate July‑to‑September typhoon‑season logistics risks into annual operations, build permanent emergency protocols, and safeguard transit performance and cost control amid market volatility.
Turbulent tides are inherent to the East China Sea; weathering pressure defines major hub ports. Typhoons pass, and congestion will eventually clear. Drawing on Ningbo‑Zhoushan Port’s hub advantages, Zhonjing leverages end‑to‑end resource integration and dynamic risk‑response mechanisms to build more robust cross‑border supply‑chain systems alongside your business.